SR 32 Widen Phase 1 |
Description: In the city of Chico from SR 99 to Forest Avenue. Add lanes in each direction including 8 foot shoulders, paved landscape median, timber guardrail and signal modifications.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Butte |
City | Chico |
Zip Code | 95928 |
Senate District |
04 |
Assembly District | 02, 03 |
Congressional District | 02, 04 |
Caltrans District |
03 |
County/State Route | Butte 32 |
Postmile Begin/End | 10.3 11.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | xx | |
Lane Miles Added (HOV) | xx | |
Lane Miles Added (Mixed) | 2 | 2 |
Peak Period Time Savings (minutes) | xx |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Chico | L Green | (530)879-6930 | lane.green@chicoca.gov | |
Design (PS&E) Phase |
City of Chico | L Green | (530)879-6930 | lane.green@chicoca.gov | |
Right of Way Phase |
City of Chico | L Green | (530)879-6930 | lane.green@chicoca.gov | |
Construction Phase |
|||||
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$3,425 | $0 | $3,425 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$6,500 | $0 | $6,500 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $9,925 | $0 | $9,925 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,200 | $0 | $1,200 | $1,231 | |||
Design(PS&E) |
$2,300 | $0 | $2,300 | $1,721 | |||
Right of Way |
$0 | $0 | $0 | $0 | |||
Construction |
$6,425 | $0 | $6,425 | $6,183 | |||
Total* | $9,925 | $0 | $9,925 | $9,134 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/2007 09/15/2010 |
|
01/01/2007 09/15/2010 |
100 | 01/01/2007 09/15/2010 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2010 10/31/2010 |
|
01/01/2010 02/28/2011 |
100 | 01/01/2010 11/01/2011 |
0 -8 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/06/2010 10/15/2010 |
|
07/06/2010 10/15/2010 |
100 | 07/06/2010 12/17/2010 |
0 -2 |
|
Begin Construction Phase
End Construction Phase |
12/31/2010 11/30/2012 |
|
06/30/2012 11/30/2013 |
100 | 06/27/2012 12/11/2015 |
0 -25 |
|
Begin Closeout Phase
End Closeout Phase |
11/30/2012 11/30/2012 |
|
11/30/2013 05/30/2014 |
75 | 12/11/2015 06/01/2016 |
-25 -24 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 06/01/2010 | 06/01/2010 | 0 | 07/29/2014 | -51 | ||
Implementation Date | 06/01/2010 | 06/01/2010 | 0 | 07/29/2014 | -51 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | xx | |
Lane Miles Added (HOV) | xx | |
Lane Miles Added (Mixed) | 2 | 2 |
Peak Period Time Savings (minutes) | xx |
Bond Funding Cost | |
---|---|
Adopted: |
$3,425,000 |
Current Approved: |
$3,425,000 |
Actual Expenditures: |
$3,425,000 |
Status as of December 31, 2023.