SR 32 Widen Phase 1

Description: In the city of Chico from SR 99 to Forest Avenue. Add lanes in each direction including 8 foot shoulders, paved landscape median, timber guardrail and signal modifications.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Butte
City Chico
Zip Code 95928
 
Senate District
04
Assembly District 02, 03
Congressional District 02, 04
 
Caltrans District
03
 
 
County/State Route Butte 32
Postmile Begin/End 10.3 11.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  xx      
Lane Miles Added (HOV)  xx      
Lane Miles Added (Mixed)  2    2  
Peak Period Time Savings (minutes)  xx      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Chico L Green (530)879-6930   lane.green@chicoca.gov
Design (PS&E) Phase
City of Chico L Green (530)879-6930   lane.green@chicoca.gov
Right of Way Phase
City of Chico L Green (530)879-6930   lane.green@chicoca.gov
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$3,425 $0 $3,425
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$6,500 $0 $6,500
Non Budgeted ETC
$0 $0 $0
 
Total**** $9,925 $0 $9,925

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,200 $0 $1,200 $1,231
Design(PS&E)
$2,300 $0 $2,300 $1,721
Right of Way
$0 $0 $0 $0
Construction
$6,425 $0 $6,425 $6,183
 
Total* $9,925 $0 $9,925 $9,134

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2007 

09/15/2010 
 

 
01/01/2007 

09/15/2010 
100  01/01/2007 

09/15/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

10/31/2010 
 

 
01/01/2010 

02/28/2011 
100  01/01/2010 

11/01/2011 


-8 
Begin Right of Way Phase

End Right of Way Phase
07/06/2010 

10/15/2010 
 

 
07/06/2010 

10/15/2010 
100  07/06/2010 

12/17/2010 


-2 
Begin Construction Phase

End Construction Phase
12/31/2010 

11/30/2012 
 

 
06/30/2012 

11/30/2013 
100  06/27/2012 

12/11/2015 


-25 
Begin Closeout Phase

End Closeout Phase
11/30/2012 

11/30/2012 
 

 
11/30/2013 

05/30/2014 
75  12/11/2015 

06/01/2016 
-25 

-24 
Corridor System Management Plan
Adoption Date 06/01/2010    06/01/2010  07/29/2014  -51 
Implementation Date 06/01/2010    06/01/2010  07/29/2014  -51 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) xx
Lane Miles Added (HOV) xx
Lane Miles Added (Mixed) 2 2
Peak Period Time Savings (minutes) xx

Bond Funding Cost
Adopted:
$3,425,000
Current Approved:
$3,425,000
Actual Expenditures:
$3,425,000

 

Status as of December 31, 2023.